Hyperia First Drop Installation Continues

Thorpe Park
Wednesday 28th February 2024

It's another busy day at the Hyperia construction site, the cranes have been busy and more of the first drop has been installed. The next stage will be more tracks being added!


More supports mirroring what was added yesterday have been added to the first drop structure. Whilst we were leaving tonight the team building the rollercoaster where having some difficulty installing one of the supports. But we're sure with time the support we saw rise into the air will be fitted and ready for more exciting changes tomorrow.


With a lot of the track now installed work is starting to turn to wiring up this massive rollercoaster. Sensors for the ride have been installed on the first turn to tell the ride's computer where the train is before it engages on the lift hill.


More supports were driven onto the site this afternoon along with a section of white track which leads us to believe that track will be lifted into place tomorrow. 


Recently Posted News Articles