The World Of Jumanji is progressing fast with big changes made across the construction site, the big animal theming element is now completely covered n metal rebar and it is close to being finished! Since our last look at the animal more of the creature has been covered in concrete and has been themed. 


At the top of the site, the foundations for one of the new flat rides have been completed. Walls can be also seen around the new ride base, we're still a long way off from seeing ride hardware for these new flat rides but it's good to see progress being made! 


Work on enclosing the ride's station has now begun with metal panels being added to the back of the station building. Metal rebar can be seen on each side of the station, ready for the station floor to be poured and installed. 


There's no sign of any rollercoaster track yet but it won't be long now until we start to see rollercoaster track and supports delivered and start to be installed over the new few months. 


Very exciting times ahead for Chessington World of Adventures!